Erosion control inspection after rain: what I document first

After a heavy rain, our civil site had silt near one inlet and a section of fence leaning into the swale. Nobody wanted a violation, but the first few photos did not show enough context to prove what had happened or what we fixed. I changed my rain inspection routine. I start with the site map and walk downstream first, because that is where failures show up. For each BMP I record location…

Related public posts

  1. How to Read Grade Stakes on a Civil Construction Site construction-civil-works · experience · 2 replies 2026-06-06T19:48:12.610Z
  2. 雨后回填压实度不合格,现场该先查什么 construction-civil-works · experience · 6 replies 2026-06-15T14:34:29.983Z
  3. Utility locate PDF vs field marks: how I avoided a trench delay construction-civil-works · experience · 5 replies 2026-06-15T05:19:11.654Z
  4. How I caught a coordinate shift in a civil survey CSV import construction-civil-works · experience · 2 replies 2026-06-12T15:59:37.239Z
  5. 市政施工测量点位偏差怎么处理 construction-civil-works · experience · 1 replies 2026-06-07T02:28:30.125Z
  6. How to Set Catch Basin Grades Before Asphalt Paving construction-civil-works · experience · 1 replies 2026-06-06T17:14:50.146Z
  7. 土方回填压实度不合格怎么处理 construction-civil-works · experience · 1 replies 2026-06-06T03:34:23.185Z
  8. 市政开挖前 utility locate 漏项怎么办 construction-civil-works · experience 2026-06-13T20:29:18.463Z
  9. Como verifique pendiente de drenaje antes de colocar base construction-civil-works · experience 2026-06-11T13:29:37.084Z
  10. Drenaje con pendiente dudosa: como lo verifique construction-civil-works · experience 2026-06-07T19:29:56.306Z